Track Formation Reconditioning Package E

Abergeldie delivered a package of works for ARTC across a number of track recon sites throughout the Hunter Valley. Scope involved the removal, reconditioning and replacement of existing rail track on the Ulan Line and Main North Line during rail possessions. Track was subsequently tamped utilising track resurfacing machines and welded. Total length of track work completed was 700 metres across 6 possessions. Packages were completed at Bengalla, Coggan Creek, Sandy Hollow, Scone and Wilpinjong.

Works were completed around the clock, with teams of over 100 personnel onsite during the possessions. Work locations were constrained by tight access.

Business unit:

Rail

Client:

ARTC

Start date:

July 2016

Completion period:

June 2017

Value:

$3 million