Project Description:
Abergeldie was contracted to construct a new road bridge over Mullet Creek at Cleveland Road, Dapto. The scope of works included removal of an existing footbridge and relocation of services including power lines and poles and a DN100 Sydney Water Main. The bridgeworks comprised of piling, excavation, concrete abutments and installation of precast decking planks, approach slabs, railings and parapets. The water had to be stabilised with new gabion walls and creek scour protection.
Awards:
Civil Contractors Federation (CCF), Category 1, 2015 Finalist
Business unit:
Engineering
Client:
Wollongong Council
Current status:
Complete
Start date:
November 2013
Completion period:
September 2014
Contract type:
Lump sum
Value:
$2.8 million