SYDNEY WATER CHEMICAL DOSING SYSTEMS UPGRADE

PROJECT DESCRIPTION:

The works, carried out under the Sydney Water Network Facility and Renewals Program (NFRP) involved upgrading 21 existing chemical dosing systems across seven Sydney Water plants. The packages included condition assessment, design, epoxy lining, new unloading bays, new dosing lines and replacing existing pumps and pipework inside the bunds. Most of the sites needed to remain operational during the upgrade, so temporary dosing systems were established so the work could be done.

Business unit:

Water

Client:

Sydney Water

Current status:

Complete

Start date:

October 2014

Value:

$5.1 million