Project description:

Earthworks and extensive drainage works for lowering, realigning and resurfacing a 200 meter section of roadway through a new underpass beneath a live railway corridor.

Complex Challenges:

Traffic management, including road closures and detours, needed to be planned in detail in cooperation with multiple local stakeholders.

Business unit:

Engineering

Client:

Rail Infrastructure Corporation

Current status:

Complete

Start date:

July 2001

Completion period:

November 2001

Contract type:

Lump sum

Value:

$0.7 million