BOTANY NITROGEN LIQUEFIER PLANT

PROJECT DESCRIPTION:

Construction of a new Nitrogen Liquefier Plant (‘OSCAL’) at the existing Botany Air Separation Unit (‘ASU’) Plant in Sydney. Work included earthworks, services and concrete works.

Complex Challenges:

Restricted work area within a Brownfield site, immediately adjacent to operating plant.

Business unit:

Petrochemical

Client:

Air Liquide Australia

Current status:

Complete

Start date:

November 2008

Completion period:

August 2008

Contract type:

Lump sum

Value:

$0.4 million