MULLET CREEK BRIDGE

Project Description:

Abergeldie was contracted to construct a new road bridge over Mullet Creek at Cleveland Road, Dapto. The scope of works included removal of an existing footbridge and relocation of services including power lines and poles and a DN100 Sydney Water Main. The bridgeworks comprised of piling, excavation, concrete abutments and installation of precast decking planks, approach slabs, railings and parapets. The water had to be stabilised with new gabion walls and creek scour protection.

Awards:

Civil Contractors Federation (CCF), Category 1, 2015 Finalist

Business unit:

Engineering

Client:

Wollongong Council

Current status:

Complete

Start date:

November 2013

Completion period:

September 2014

Contract type:

Lump sum

Value:

$1.7 million