PROJECT DESCRIPTION:

Supply, installation and commissioning of an upgraded aeration system and associated controls and services.

Complex Challenges:

Works were carried out on a brownfield site adjacent to operating systems, requiring close attention to safe work methods and careful scheduling of work and cut-ins to prevent interruption to continuous plant operation.

Business unit:

Water

Client:

Hunter Water Corporation

Current status:

Complete

Start date:

September 2009

Completion period:

July 2010

Contract type:

Lump sum

Value:

$1.1 million